Annual output of 5000 tons of electronic special gases project
Site Area
Total Plant Site Area: 133,103.29 square meters.
Construction Location
Eastern District, Lingang Economic & Technological Development Zone, Bohai New Area, Cangzhou City, Hebei Province, China
Project Scope
This project primarily involves the construction of production units, utility facilities, and auxiliary production facilities. The main components include:
Production Units:
Cold Hydrogenation Unit
Disproportionation Unit
Tail Gas Scrubber
Silane Filling Station
Filling/Packaging Room
Storage Facilities:
Tank Farm I
Tank Farm II
Pump Shed
Loading/Unloading Shed
Storage Shed
Utility Facilities:
Wastewater Pretreatment
Wastewater Evaporation
Sewage/Wastewater Treatment Plant (WWTP)
Power Station
Circulating Water Pond
35kV Substation & Power Distribution Station
10kV Power Distribution Room
Instrument/Control Room
Auxiliary Production Facilities:
Incinerator
Ground Flare
Fire Water Station
Emergency/Surge Pond