Tianjin petrochemical enterprises have been focusing on construction to boost production and actively carrying out Quality Day activities
The key milestones of the Tianjin Bohua Phase II project cluster of China National Chemical Tianchen Company have been achieved
On April 8th, it was learned from China National Chemical Tianchen Company that recently, the PVC project of the Bohua Phase II project Group, which was constructed by China National Chemical Tianchen Company, has successively completed three core milestone nodes: the successful first power reception of the 35kV and 10kV high-voltage systems of the PVC substation, the successful first power reception of the 10kV system of the public auxiliary low-voltage substation, and the successful single-machine test run of the circulating water pump motor. This marks the official entry of the project into the comprehensive equipment commissioning stage, laying a solid foundation for the subsequent material feeding and trial operation.

The "Two Modernizations" relocation and transformation project of Tianjin Bohua is a key project in Tianjin. After its completion, it will be conducive to promoting energy conservation, emission reduction and environmental improvement, driving the adjustment and transformation and upgrading of enterprise structure, and optimizing urban space and industrial layout. During the construction process, in the face of challenges such as tight schedules and complex cross-operations, the project team of Tianchen Company scientifically coordinated resources, optimized the construction path, strictly controlled safety and quality risks, and carried out multiple rounds of joint inspections with the owner and the supervision unit to ensure zero errors in the power receiving process. During the trial run of the circulating water pump, an intelligent monitoring system is adopted to collect real-time data such as vibration and temperature, accurately verify the performance of the equipment, and achieve "meeting standards upon trial run". At present, the project team is fully committed to advancing subsequent work such as the pressure testing of process pipelines and the integrated debugging of the DCS system, and is making a final push towards the full delivery of the project.
The successful completion of these three nodes this time demonstrates Tianchen Company's professional strength in the field of engineering general contracting. In the future, the project department will continue to act with a strong sense of responsibility and mission, sparing no effort to advance the project construction, ensuring that the subsequent material input and trial run goals are achieved on schedule, and injecting strong impetus into the high-quality development of the project. (Qu Zhaogui, Correspondent of China Chemical Industry News, Liu Huayi
The Jintang project of the Ningbo region of Petrochemical Transportation Company has witnessed a vigorous construction boom
On April 8th, it was learned from the Petrochemical Transportation Company that recently, the construction site of the Jintang project in the Ningbo area of the Petrochemical Transportation Company has been receiving good news frequently. The 400-ton phenol acetone plant's separation tower was successfully positioned under the precise operation of a 1,600-ton crawler crane, marking that the hoisting of the main equipment of this project has entered a critical stage.
It is reported that the partition tower, as the tallest and heaviest equipment in the phenol-acetone plant, has high hoisting risks and strict node requirements. The project department has formulated a special plan and emergency measures, fully leveraging the advantages of regional management and resources, allocating regional elite personnel, and concentrating efforts to tackle the "tough nuts to crack". Thanks to the efforts of the construction teams in the Ningbo area and the Jintang project, the partition towers were safely hoisted into place at the designated nodes.
While the construction of the partition tower was underway, the project construction team was simultaneously advancing each key node: the project team safely and efficiently completed the unloading and transportation tasks of two cold boxes for the air separation unit, three deaerators and other large equipment at the wharf, and accomplished the hoisting and dismantling of the 750-ton crawler crane, ensuring the smooth operation of the 750-ton crawler crane at the next project construction node. (Qu Zhaogui, correspondents Han Zhiyu and Wang Yubo of China Chemical Industry News
All the grassroots units of the Fourth Construction Company of Sinopec actively carried out the Quality Day activities
On April 7th, the project departments of the Second Engineering Company of Petrochemical Fourth Construction Company actively responded to the quality work deployment of Petrochemical Fourth Construction Company. With the theme of "Innovating Quality Management and Driving Value Creation", they organized and carried out various forms of Quality Day activities. Quality Day kick-off meetings were held at each project site. Through a series of activities such as problem source analysis, organizing special inspections, and "chief engineers giving lectures", the quality management level of the projects was comprehensively enhanced. During the event, the project department also commended outstanding individuals, organized the participants to sign commitments, and hung quality-themed banners to further strengthen the quality responsibility awareness of all staff and create a strong quality culture atmosphere. (Jiao Wenpei
On the morning of April 8th, the project department of the Fourth Construction Company of Sinopec held the launch ceremony of the 2025 Quality Day, comprehensively arranging the annual quality improvement work. More than 120 management personnel from the Sinopec Quality Supervision Station, the owner of the Research Institute of Petroleum, Beijing Huaxia Supervision, Guangzhou Engineering Company, and the project department gathered at the project site of the Research Institute of Petroleum, focusing on the theme of "Innovating Quality Management and Driving Value Creation". Everyone signed solemnly on the banner, promising to guarantee the quality of the project.
Subsequently, the first session of the "Chief Engineer's Lecture" of the engineering project department was launched. The chief engineer of the project, based on the actual engineering situation, explained the key points of technical quality control, bringing a rich and highly practical training class to the people present, helping everyone better understand and implement technical quality management work.
Subsequently, the project department of the Petroleum Research Institute of Sinopec Fourth Construction Company will thoroughly implement the policy of "quality always leading by one step", strengthen quality control throughout the entire chain, strictly benchmark against the "Key Points of Quality Work of Sinopec in 2025", build a full life cycle quality management system, and promote the quality improvement and upgrading of the project construction of the Petroleum Research Institute. (Hu Min
Recently, in response to the company's quality work deployment, the South China Branch of Sinopec Fourth Construction Company has actively organized various forms of Quality Day activities under the theme of "Strengthening Quality Awareness and Creating Quality Projects" in its project departments. During the event, each project department popularized quality management knowledge among all employees by holding quality knowledge lectures and conducting quality case analysis meetings, etc., to enhance their quality awareness. At the same time, a comprehensive quality inspection at the construction site was organized. Any problems found were promptly rectified to ensure that the project quality met the standard requirements.
Through this Quality Day event, the project departments of the South China Branch have further strengthened the quality awareness of their employees and improved the level of engineering quality management.